1.What’s Being Built in Queen Creek Right Now (September 2026)
Status is what the named source said on the date in the last column, not what a press release said at announcement. Where no completion date is published, the table says so.
| Project | Where | Status | Expected | Source date |
|---|---|---|---|---|
| LG Energy Solution (cylindrical EV cells) | Ironwood & Germann, NEC | Under construction | Production summer–late 2026, per the window across sources | Town page (“late 2026”), Sept. 20, 2026; trade press (summer 2026), May 2026 |
| LG Energy Solution ESS (LFP pouch cells) | Same site | Paused, no confirmed restart | None published | Paused 2024; on hold per May 2026 trade press |
| The Switchyard, Phase 1 commercial | Ellsworth & Ocotillo, NEC | Under construction | Opening Q4 2026 into Q1 2027, per the Town’s own August 2026 deck; Postino scheduled as the first tenant, early October 2026. Earlier mid-2026 and Q3 2026 targets have been overtaken | Town downtown slide deck, Aug. 2026; status re-checked on the Town tracker, Sept. 20, 2026 |
| The Switchyard, 215 apartments | Same 10-acre site | In design as of mid-2025; the Town lists the multifamily phase as “TBD” | Not published | AZ Big Media, June 14, 2025; Town downtown slide deck, Aug. 2026 |
| The Perch | Munoz St., off Ellsworth | Under construction | End of 2026, as reported | Status: Town tracker, Sept. 20, 2026; target: QC Tribune, Nov. 2025 |
| Rusty Buckle Saloon | 21838 S. Ellsworth Rd. | Under construction | Its only published target was mid-2026, which the project has already gone past; nothing newer found | Status: Town tracker, Sept. 20, 2026; target: QC Tribune, Nov. 2025 |
| The Matheson (offices) | Ellsworth Loop & Ocotillo | Under construction | Not published | Town tracker, Sept. 20, 2026 |
| Magma Plaza | Former Magma Engineering building | Under construction | Not published | Town tracker, Sept. 20, 2026 |
| Homewood Suites | Downtown | Under construction | Not published | Town tracker, Sept. 20, 2026 |
| QC Accounting | Downtown | Under construction | Not published | Town tracker, Sept. 20, 2026 |
| Circle K rebuild | Ellsworth & Ocotillo, NEC | Now open | — | Town tracker, Sept. 20, 2026 |
| Sweet Creek Boutique | Downtown | Now open | — | Town tracker, Sept. 20, 2026 |
| Police headquarters, $96M | Ellsworth Rd., north of Crewse Ln. | Under construction; ground broken June 2026 | Completion “currently anticipated in 2028” (Town); July 2028 per May 2026 reporting | Town release, June 8, 2026 |
| Fire station, southern town | Site not published | Design funded only | Not published | Town budget, May 21, 2026 |
| Banner Ironwood ER and imaging addition | 37000 N. Gantzel Rd. | Under construction | December 2027 | Banner Health, Aug. 28, 2026 |
| Recreation & Aquatic Center | Frontier Family Park | Open | Opened March and May 2025 | Town release, March 25, 2025 |
| SR 24 widening, Ironwood diverging diamond | Loop 202 to Ironwood Dr. | Designed, not started | Construction anticipated early 2027 | ADOT, Sept. 20, 2026 |
| SR 24 extension toward US 60 | East of Ironwood Dr. | Unfunded study only | None exists | ADOT, Sept. 20, 2026 |
| Ellsworth Rd. widening (City of Mesa) | Germann Rd. to Ray Rd. | Under construction | Completion expected February 2027 | Town update posted ~Dec. 2025; Phase 1 started Jan. 5, 2026 |
| Sossaman and Germann intersection | Germann Rd., Sossaman to Rittenhouse | Funding identified, start not published | Not published | Town page, Sept. 20, 2026 |
| Crismon Rd. extension (“Chrisman” in CIP summaries) | Cloud Rd. to Riggs Rd. | Reported underway, Phases II–III | Not published | Town CIP updates, Feb.–May 2025 |
| QCUSD: 2 elementaries, Crismon additions | Elementary sites not selected; the additions are on the existing Crismon campuses | Requested, not awarded | Elementaries before 2029; additions by 2031 | Queen Creek Tribune, Aug. 2025 |
Most downtown rows come from one continuously updated source: the Town economic development office’s downtown project page, which carries a live status label per building. It tells you to check it for future updates, so do exactly that before trusting any status here.
2.Downtown Queen Creek: The Switchyard, The Perch and the Ellsworth-Ocotillo Block
Downtown carries about $200 million in private investment and roughly 230,000 square feet of commercial space, per the Town — its release posted January 14, 2026 said “nearly $200 million,” and its downtown page now says “more than.” Either way the comparison is the point: roughly 4,000 square feet of active commercial construction downtown in 2023. That is the whole story of downtown in two numbers, for a town that only incorporated on September 5, 1989. Sales from those buildings get taxed at the rates in our Queen Creek sales tax breakdown.
The Switchyard
$120 million on 10 acres at the northeast corner of Ellsworth and Ocotillo, developed by Creation with Horizon Real Estate Ltd., designed by GFF Design, built by LGE Design Build, ground broken May 7, 2025. Phase 1 is commercial; 215 apartments were in design as of June 2025, and the Town’s August 2026 downtown slide deck still lists that multifamily phase as “TBD.” The commercial space is reported as 54,000 square feet at groundbreaking, 48,000 square feet for Phase 1 in November 2025, and 47,950 square feet of restaurant, retail and office space in that August 2026 Town deck — the newest of the three, and effectively the November figure again. The same deck puts the opening in the fourth quarter of 2026 into the first quarter of 2027, with Postino scheduled to be the first tenant to open, in early October 2026.
The rest of the block
The Perch is 62,000 square feet of brewery, retail and restaurant space on Munoz Street, expected at the end of 2026 per a November 2025 report. Rusty Buckle Saloon is a country-themed 8,930-square-foot bar and restaurant at 21838 S. Ellsworth Road. The Matheson adds 20,000 square feet of offices at Ellsworth Loop and Ocotillo, and Magma Plaza converts the former Magma Engineering building into an 8,500-square-foot plaza. A Homewood Suites and QC Accounting finish the Town’s roster, alongside a rebuilt Circle K and Sweet Creek Boutique, both listed open.
Two mid-2026 targets have come and gone: The Switchyard was given mid-2026 at groundbreaking, and Rusty Buckle Saloon was targeting mid-2026. A November 2025 report then moved The Switchyard to the third quarter of 2026, and the Town’s own August 2026 slide deck moved it again, to the fourth quarter of 2026 into the first quarter of 2027. That is three published windows for one building between June 2025 and August 2026. Rusty Buckle has no newer target than mid-2026 in any source here, and the Town’s tracker still listed both projects as under construction on September 20, 2026.
3.What Are the Newest Restaurants in Queen Creek?
The honest answer for September 2026 is that the publicized names are signed, not serving — but one of them has a date. The Town’s own August 2026 downtown slide deck says Postino is scheduled to be The Switchyard’s first tenant to open, in early October 2026, with the rest of the center following in the fourth quarter of 2026 into the first quarter of 2027. Every other tenant below was announced for a downtown project the Town still lists as under construction. The first four come from the developer’s own site and trade-press coverage of the May 2025 groundbreaking; the second wave was reported on March 10, 2026 and was not all food, pairing Bamboo Sushi, described as an Arizona market debut, with ROOM and PORCH, Zara Nail Bar and Edward Jones.
| Tenant | Project | Announced | Open yet? |
|---|---|---|---|
| Postino | The Switchyard | May–June 2025 | Not open yet; the Town’s Aug. 2026 deck schedules it first, in early Oct. 2026 |
| Shake Shack | The Switchyard | May–June 2025 | Not open |
| Snooze A.M. Eatery | The Switchyard | May–June 2025 | Not open |
| The Porch | The Switchyard | May–June 2025 | Not open |
| Bamboo Sushi | The Switchyard | March 10, 2026 | Not open |
| ROOM and PORCH | The Switchyard | March 10, 2026 | Not open |
| Zara Nail Bar | The Switchyard | March 10, 2026 | Not open |
| Edward Jones | The Switchyard | March 10, 2026 | Not open |
| Rusty Buckle Saloon | Standalone, S. Ellsworth Rd. | Reported Nov. 2025 | Not open |
| The Perch | Standalone, Munoz St. | Reported Nov. 2025 | Not open |
Cornerstone at Queen Creek is not a construction project
It is the open, Walmart Supercenter-anchored center at the northwest corner of Rittenhouse and Ocotillo, owned by WDP Partners in a joint venture with the original property owner. No expansion or new construction there appeared in any source used for this tracker. The developer’s own page describes a 340,000-square-foot power center, but that page content is dated 2018, and an aggregator figure above 380,000 square feet could not be verified. For the centers and stores already trading, see our guide to shopping in Queen Creek.
4.LG Energy Solution: What Is Under Construction, and What Is Paused
One plant is being built and one is not. The cylindrical EV battery plant, which the Town describes as a one-million-square-foot building, is under construction on about 300 developed acres at the northeast corner of Ironwood and Germann. The energy storage systems plant, the LFP pouch line, had its construction paused in about June or July 2024, and no Town or company source confirmed a restart as of September 20, 2026.
The Town’s page put the facility at about 60% complete in August 2025, targets 1,500 jobs once the cylindrical plant is fully operational, and says about 150 employees had been hired through February 2026 — a figure still unrefreshed seven months later. Workers have trained at Central Arizona College’s Superstition Mountain Campus through the Future48 Workforce Accelerator. If you are timing a move around production start, build in slack and work from the 30-day relocation checklist.
| Figure | What it refers to | Source and date |
|---|---|---|
| $5.5 billion (KRW 7.2 trillion) | Announced capital investment for the whole Arizona complex, both plants | Town of Queen Creek, April 3, 2024, still its headline figure in Sept. 2026 |
| $3.2 billion | A later reported capital figure for the cylindrical plant, the phase still being built | Connect CRE, syndicating Phoenix Business Journal, May 2026 (secondary) |
| $4.3 billion | The value of an agreement to supply energy storage batteries to Tesla — a contract, not construction, with no production site stated | Connect CRE, May 2026 (secondary) |
| $84,444,000 | What the 650.5-acre State Land parcel under the complex sold for on April 19, 2022, on a single bid at the minimum price | Arizona State Land Department auction history, April 2026 |
The Tesla supply agreement is not evidence that the paused plant restarted — they are separate items in separate sources. Anyone saying the second plant is building again should be able to point at a Town or company statement, and as of September 20, 2026 there is none. More on the plant and its workforce in our guide for incoming LG Energy Solution staff.
5.Road Projects: SR 24, Ellsworth, Sossaman and Germann
Road work changes your day before any building does. One project is already restricting traffic: the City of Mesa’s Ellsworth Road widening, whose first phase started January 5, 2026 and cut northbound Ellsworth to one lane around the clock — not along the whole Germann-to-Ray job, but through Phase 1’s Segments 1 and 2, from Germann Road to Pecos/Willis Road. Mesa has not published how long that restriction lasts; the only published date is February 2027 for the project overall. Weigh it against our comparison of Queen Creek neighborhoods if you are choosing between addresses on that corridor.
| Project | Scope | Funding | Timing |
|---|---|---|---|
| SR 24 widening (ADOT) | Two added lanes each way from Loop 202 to Williams Field Rd., one each way on to Ironwood Dr., the Ironwood interchange rebuilt as a diverging diamond, plus new Ellsworth–Loop 202 connector ramps | Partly Proposition 479, the Maricopa County half-cent transportation tax approved in 2024 | Design completed spring 2026; construction anticipated to begin early 2027 |
| Ellsworth Rd. widening (City of Mesa) | Three lanes each way from Germann Rd. to Ray Rd. with signal upgrades, landscaping and signage, in three phases | A City of Mesa project, publicized by the Town | Phase 1 (northbound lanes, Segments 1–2, Germann Rd. to Pecos/Willis Rd.) began Jan. 5, 2026, northbound down to one lane 24/7 through that segment; overall completion expected February 2027 |
| Sossaman Rd. and Germann Rd. | Extends Germann from Sossaman to Rittenhouse, widens it to three lanes each way, adds an at-grade railroad crossing with rail-safety measures; framed by the Town as an alternative route to Ellsworth | $24–28 million total, up to $18 million from Proposition 479; $1.7 million design cost shared with Mesa and Maricopa County | Town says most funding is available in 2026; no construction start published |
| Crismon Rd. extension (spelled “Chrisman” in CIP summaries) | Cloud Road to Riggs Road with new roundabouts and pedestrian facilities, staged to keep school access open | Town capital improvement program | Phases II and III reported underway in Town CIP updates from February and May 2025 |
| FY2026/27 town road program | Power Rd. (Chandler Heights to Riggs), Hawes Rd. (Rittenhouse to Jude), Sossaman Rd. (Sonoqui Wash to Chandler Heights), Chandler Heights Rd. (Sossaman to Hawes), Hawes Rd. (Chandler Heights to Ocotillo) | $71.1 million for transportation improvements | Budget effective July 1, 2026 |
The SR 24 extension east of Ironwood Drive toward US 60 is not funded and has no construction timeframe. ADOT’s own page describes a Pinal County-led feasibility study, nothing more. Anything treating that extension as coming is describing a study, not a road.
Two things the list does not contain. No standalone widening project names Riggs Road or Signal Butte Road as its primary road: Riggs turns up only as an endpoint of other projects, and Signal Butte only in a secondary source discussing a possible future SR 24 interchange. And the Meridian Road corridor is history rather than current work: that groundbreaking release is dated January 2022 and an October 2022 report described the project as nearing completion. No primary source fixes a completion date, so the honest statement is that it appears to have finished around 2022 or 2023 and is not a current construction project. Near the plant, a February 2025 Town CIP update described crews building the northbound lane on Ironwood Drive and the first half-mile of Pecos Road for delivery in late 2025; nothing fresher confirms that it finished.
6.Police Headquarters, a Fire Station, a Hospital Wing and the Rec Center That Already Opened
The police headquarters is the biggest public building on the list: $96 million on Ellsworth Road north of Crewse Lane, near Summers Place, between Fire Station No. 1 and the Community Chambers. Council approved more than $11.3 million in related agreements on May 20, 2026 with design 90% complete, and the Town announced on June 8, 2026 that it had broken ground, closing Crewse Lane between Summers Place and Ellsworth Road until construction finishes — currently anticipated in 2028, which the May 2026 reporting put more precisely at July 2028. The Town splits the $96 million into $21 million growth-related, paid by police impact fees and dedicated construction sales tax on new development, and $75 million non-growth, paid mainly from pay-as-you-go reserves. Do not read the FY2026/27 budget’s $106.1 million for Police Master Plan facilities as the same number: that is a budget category, and no source used here splits it by building. How a capital program this size shows up on a tax bill is covered in our property tax guide.
- New fire station, southern area of town — design only. The FY2026/27 budget includes $4.5 million for fire and medical facilities and equipment, including design of a new southern station. No site, groundbreaking date or construction timeline is published.
- Banner Ironwood Medical Center — under construction. A 32,000-plus-square-foot addition at 37000 N. Gantzel Road broke ground August 27–28, 2026: a two-story building on the existing Emergency Department, an interventional radiology suite with pre-op and post-op space, and an expanded ER lobby. Archsol is architect, Mortenson contractor, completion slated December 2027. Where the hospital sits among the area’s other options is covered in our guide to hospitals and urgent care.
- Queen Creek Recreation & Aquatic Center — already open. The recreation and aquatic center opened March 29–30, 2025 and the aquatic side in May 2025. It is not a construction project any more, whatever an older article says.
The $157 million figure attached to the Recreation & Aquatic Center in older coverage is a three-project total — the Town’s groundbreaking release covers that center, Frontier Family Park and Mansel Carter Oasis Park Phase II together. A separate $65 million figure for the center alone comes from an aquatic design firm, not the Town. No source reconciles the two, and the packs behind this page do not fix a construction start month either.
One caution on the hospital. A separate, undated description of a larger Banner Ironwood expansion involving cardiac services and a bed count circulates in trade-press results. It does not match the August 2026 release, the two could not be reconciled, and only the August 2026 release is reflected above.
7.Are New Schools Being Built in Queen Creek?
Not yet — they are requested. The Queen Creek Unified School District capital plan, as reported in August 2025, asks the state School Facilities Division to fund two new elementary schools at 750 K–6 students each, opening before 2029, plus additions at Crismon Junior High and Crismon High School of 500 students of capacity each, projected to open by 2031. No site has been chosen: the district holds five vacant parcels under consideration. Which campuses serve which addresses today is a different question, and our Queen Creek schools guide is where to start on it.
The funding route matters more than the drawings. QCUSD has no active bond funding: as of August 2025 reporting, the district’s last two bond requests had been rejected by voters, and the 2024 override passed — the certified county canvass for November 5, 2024 records 53.71% yes, 22,177 votes to 19,115, for a 15% maintenance-and-operations override running six years. The county’s election list shows no QCUSD measure at all in 2025. That measure is a maintenance-and-operations override, not a construction bond, so the buildings still depend on state awards. The division reviews district capital plans annually, with plans due September 1 and awards made in December, and construction begins in the winter after an award. No award had been confirmed in any source available for this tracker.
The demand behind the request is measurable. The state report card page for QCUSD listed 15,034 students when we checked it on September 20, 2026. Reporting from August 2025 put enrollment growth at more than 5,000 students over five years, to 14,589 at that point, and projected roughly 17,500 by 2034–35.
8.The Northeast Growth Area: What Has Not Been Auctioned
The battery complex exists because of one land auction. On April 19, 2022 the Arizona State Land Department sold a 650.5-acre parcel at the northeast corner of Ironwood Drive and Germann Road, plus smaller adjoining rights-of-way, for $84,444,000 to ES America, LLC, on a single bid at the minimum price. New rooftops in the same corridor come from private master plans instead; our rundown of the builders active in Queen Creek covers who is selling there.
The more useful finding is a negative one. A larger 914.78-acre parcel at the northwest corner of Ironwood and Germann, minimum bid $86,130,000, was postponed repeatedly through 2021 and then recorded as Auction Cancelled as of December 1, 2021. No re-auction appears in the department’s own auction history through April 2026 — and that document, running from FY2017 to the present, holds no Queen Creek-area auction entry of any kind after the April 2022 sale.
Claims about a new corporate land deal in the northeast growth area are not supported by the state’s own auction record as of April 2026. What the cancelled parcel does next could not be verified from a primary source. Open the auction history PDF yourself before repeating anything about it.
9.How to Follow Along Yourself
Every fact above came from a page you can open. Work through them in this order, and remember that a status without a date is a rumor.
- Start with the Town’s downtown project page. It is the only source carrying a current status label per building, and it settles arguments about whether something is open.
- Use the Town’s capital-projects portal for anything with a road name in it. Projects are listed by number and name, so you can follow one intersection across budget years.
- Search the Town’s current planning and zoning cases for your nearest cross-streets before assuming a vacant parcel stays vacant. Cases appear there long before dirt moves.
- For the battery plant, read the Town’s economic development page and write down the date attached to the hiring figure — it read February 2026 when we checked in September 2026.
- For SR 24, go to ADOT rather than the Town, and download the fact sheets linked from the project page.
- Note the date you checked, the way every row above does.
| What you want to know | Where it is published | What to expect |
|---|---|---|
| Whether a downtown building is open or still under construction | InvestTheQC downtown Queen Creek project page, and the Downtown Vibes slide deck linked from it | A live status label per project, plus the deck’s per-project opening windows — the source behind most labels and dates in this guide |
| Status and budget of road and capital projects | The Town’s ClearGov capital-projects portal | Projects by number and name, including Sossaman and Germann, Power Road and State Route 24 |
| What development is being reviewed right now | Town current planning and zoning cases | Active development-review cases, long before dirt moves |
| Battery plant milestones and hiring | Town economic development page for LG Energy Solution | Check the date on the hiring figure before quoting it; it read February 2026 in September 2026 |
| State highway work on SR 24 | ADOT State Route 24 project page | Current schedule plus downloadable fact sheets — go here, not to the Town |
| State trust land auctions nearby | Arizona State Land Department auction history PDF | The April 2026 edition shows no Queen Creek auction after April 2022 |
Numbers you will see reported two ways
| Number | Reported as | Also reported as | How we handle it |
|---|---|---|---|
| Switchyard commercial space | 54,000 sq ft, June 2025 | 48,000 sq ft for Phase 1, Nov. 2025; 47,950 sq ft in the Town’s Aug. 2026 deck | All three, with dates; the Town’s own 2026 figure is the newest |
| Switchyard apartments | 215 units, June 2025 | 206 units on the developer’s site | Use 215, and note the developer shows both; the Town lists the phase itself as TBD |
| Switchyard opening | Mid-2026, June 2025; Q3 2026, Nov. 2025 | Q4 2026 into Q1 2027, Town deck, Aug. 2026 | Quote the Town’s 2026 window and check its page for a newer one |
| Recreation & Aquatic Center cost | $157 million | $65 million | The larger figure is a three-project total; the smaller is a design firm’s, not the Town’s |
| LG Energy Solution investment | $5.5 billion, 2024 | $3.2 billion, 2026 | Different scopes and dates — see the table above |
| Cornerstone at Queen Creek size | 340,000 sq ft, developer page | Over 380,000 sq ft, aggregators | Prefer the developer figure; its page content is dated 2018 |
| The road east of the high school | Spelled Crismon | Spelled Chrisman in CIP summaries | Same road — search both spellings |
One boundary to keep straight while you search: San Tan Valley has been its own incorporated town since September 17, 2025, and its projects do not appear on Queen Creek’s trackers or in this guide. Our side-by-side of the two communities covers what else changed at that line.